Garden Rapids at The Big Pool project is on schedule
As seen in The Garden City Telegram, by Meghan Flynn. (March 19, 2021)
The Garden City City Commission was updated on the status of the Garden Rapids at The Big Pool project at its regular meeting Tuesday.
Todd Dumler, project manager with McCownGordon, reported the project is on budget and on schedule.
There was a delay in February due to the extreme cold, but they were able to mitigate it, Dumler said. They knew bad weather was coming, so they re-sequenced some of the on-site schedule, such as installing two of the slides — a blue tube slide and an orange body slide.